Please login to use this feature. You can use this feature to add the product to your favourite list.
Close
You have added this product to your favorite list. Check My Favourite
Close
You have removed this product from your favourite list.
Close
Please login to use this feature. You can use this feature to add the company to your favourites list.
Close
This company has been added successfully. Check My Favourite
Close
This company has been removed from your favourite list.
Close
Please login to use this feature. You can use this feature to add the company to your inquiry cart.
Close
This company has been added to your inquiry cart.
Close
This company has been removed from your inquiry cart.
Close
This product has been added to your inquiry cart.
Close
This product has been removed from your inquiry cart.
Close
Maximum number of Product/Company has been reached in inquiry cart.
Close
Green Energy Automation Sdn Bhd
Green Energy Automation Sdn Bhd 201201043627 (1028104-T)
Business
Hours
Monday - Friday 9:00 AM - 6:00 PM
Saturday 9:00 AM - 1:00 PM
Sunday Closed
Open Closed
Onesync AI SSM
60187891859
mychinkee WeChat QR
WeChat QR

Wechat ID: mychinkee

Civil Engineering HELP

10-Aug-2025

Sharing a quick reference productivity sheet for various construction activities. This helps in planning, estimating labor requirements, and improving site efficiency.  

(plz note : some units in the shared image were incorrect, please refer below details for accurate refrence)
Excavation & Earthwork
• Manual Excavation 1.5 – 2.0 m³ per labour/day
• By JCB 60 – 80 m³ per hour
• By Poclain (200) 100 – 150 m³ per hour
• Roller Compaction 200 – 250 m³ per day
Concrete Works
• Manual Mixing 1.5 – 2.0 m³ per labour/day
• Manual Laying 3 – 4 m³ per labour/day
• Placement by Pump 20 – 30 m³ per hour
• Curing (Ponding) 1 labour per 100 m²
• Shuttering 1.2 – 1.5 m² per labour/day
Reinforcement Work
• Cutting, Bending, Tying 100 – 150 kg per labour/day
• Fixing (Columns/Beams) 80 – 120 kg per labour/day
• Fixing (Slabs/Footings) 100 – 150 kg per labour/day
Masonry
• Brick Masonry (Manual) 0.2 – 0.25 m³ per labour/day
• Brick Masonry (Machine Mixing) 0.3 – 0.4 m³ per labour/day
• AAC Block Masonry 0.5 – 0.7 m³ per labour/day
Plastering & Finishing
• 12mm Plaster 8 – 10 m² per labour/day
• 20mm Plaster 6 – 8 m² per labour/day
• Putty 12 – 15 m² per labour/day
• Painting (1 coat) 15 – 20 m² per labour/day
• Tiling 3 – 4 m² per labour/day
Road & Paving
• PCC (Manual Mixing) 1.5 – 2.0 m³ per labour/day
• Asphalt Laying 25 – 30 m² per labour/day
• Kerb Stone 30 – 40 m per labour/day
• Paver Block 5 – 7 m² per labour/day
A helpful guide for quantity estimation, productivity planning, and monitoring progress on-site.
These values serve as general guidelines. Actual productivity may vary based on site conditions, labour skill, weather, and equipment used.

Main Office

Green Energy Automation Sdn Bhd 201201043627 (1028104-T)
No. 2, Jalan Selatan 3/2, Taman Perindustrian Ringan Pulai, 81300 Skudai, Johor, Malaysia.

Tel:

Email:
Website: https://www.geasb.com
Website: https://geasb.newpages.com.my/
Website: https://geasb.onesync.my/

Browse by : Home - Classifieds - Companies - Location - Tags - Products - News & Promotion - Job Vacancy - Mobile Website - Google - SEO Results

NEWPAGES

  • BR 34719
  • US 13842
  • VN 4105
  • GB 3268
  • MX 3193
  • AR 2840
  • CN 2059
  • CO 1711
People Online
Seni Jaya Logo
Brochure
Download
Our PackageContact Us