Client Industry: Engineering & Manufacturing
Route: Singapore to Johor Bahru
Service Provided: Bilingual project coordination, import documentation, bonded cargo management
Background
A Japanese engineering company was expanding their Southeast Asia operations by setting up a new factory in Johor. Their heavy equipment and tools were staged in Singapore and had to be delivered with strict timing and documentation standards. They also required Japanese-speaking support and a detailed project timeline.
Challenges
-
Language barriers in customs and documentation
-
High-value equipment needing careful handling
-
Complex import license and bonded cargo procedures
-
Cultural expectations for punctuality and accuracy
Our Solution
We assigned a bilingual logistics manager fluent in Japanese and English to oversee all coordination.
We also:
-
Helped classify their goods under the correct HS codes for machinery
-
Applied for temporary bonded cargo clearance under project exemption
-
Managed staggered deliveries to align with the client's construction timeline
All documents were submitted in both English and Japanese for client transparency and approval.
Result
The factory setup was completed two weeks ahead of schedule. Our client praised the professionalism, bilingual support, and smooth experience, later engaging us for monthly spare parts delivery to their Johor site.