- Piping work system and flatten the ground works in progress at Malacca Pindah 5, Malacca04-Mar-2025

- Site visit, clearing and measurement site land at Taman Tasik Utama, Malacca03-Mar-2025

- Painting works exterior and interior wall at Site Bukit Katil, Malacca03-Mar-2025

- Installation door and table top kitchen tile at Site Bukit Katil, Malacca25-Feb-2025

- Installation railing corridor and clearing house at Site Bukit Lintang, Malacca (RENOVATION)25-Feb-2025

- Installation garden fence house at Sites Bukit Lintang, Malacca (RENOVATION)25-Feb-2025

- Imprint Concrete balcony works at Sites Bukit Lintang, Malacca (RENOVATION)25-Feb-2025

- Terrace waterproofing apply progress at Sites Bukit Lintang, Malacca (RENOVATION)25-Feb-2025

- Installing sliding door and tv cabinet at Sites Bukit Lintang, Malacca (RENOVATION)28-Jan-2025

- Installing sanitary ware, fittings and mirror to wall at sites Bukit Lintang, Malacca (RENOVATION)27-Jan-2025

- Finishing and checking lamp works sites at Bukit Lintang, Malacca (RENOVATION)27-Jan-2025

- Installation kitchen cabinet at Site Bukit Lintang, Malacca (RENOVATION)27-Jan-2025

- Installing window and door grill at Sites Bukit Lintang, Malacca (RENOVATION)27-Jan-2025

- Finishing wall tile entrance at Sites Bukit Lintang , Malacca (RENOVATION)27-Jan-2025

- Installation fan & lamp at Bukit Lintang, Malacca ( RENOVATION )27-Jan-2025

- Outdoor view house at Sites Bukit Katil, Malacca27-Jan-2025

- Flatten the ground works around the house at Sites Bukit Katil, Malacca27-Jan-2025

- Installing sanitary ware, bathroom accessories and kitchen hood at Site Bukit Katil, Melaka27-Jan-2025

- Installing Stainless Steel Hood Ducting Cap works at Site Bukit Katil, Malacca27-Jan-2025

- Mainhole progress works at Site Bukit Katil, Malacca27-Jan-2025

- Installing window, door and mainhole works at Sites Bukit Katil, Malacca27-Jan-2025

- Table top kitchen and kitchen cabinet view at Site Ayer Barok, Jasin Malacca (RENOAVTION)27-Jan-2025

- Outdoor view at Site Ayer Barok, Jasin Malacca (RENOVATION)27-Jan-2025

- Interior view house at Site Ayer Barok, Jasin Malacca (RENOVATION)27-Jan-2025

- Flatten the ground works around the house at Sites Malacca Pindah 5, Malacca27-Jan-2025

- Progress TNB pole installation at Project Site Malacca Pindah 5, Malacca31-Dec-2024

- Lintel and cupping works on progress at Taboh Naning, Malacca11-Dec-2024

- Roof tile installation works at Site Malacca Pindah 5, Malacca11-Dec-2024

- Installing window & door frame works at Site Malacca Pindah 5, Malacca11-Dec-2024

- Roof trusses installation works Project at Site Malacca Pindah 5, Malacca11-Dec-2024