Scope of Work:
-
Site Inspection & Assessment
Conduct detailed inspection of the existing AHU and cooling coil to assess condition, sizing, and replacement requirements. -
System Shutdown & Safety Lockout
Safely isolate and shut down the AHU system, following proper Lockout/Tagout (LOTO) procedures to ensure safety during works. -
Dismantling of Existing Coil
Remove access panels and carefully disconnect chilled water or refrigerant lines, electrical connections, and supports. -
Removal of Damaged Coil
Extract the old or leaking coil with proper handling to avoid damage to surrounding AHU components. -
Supply of New Cooling Coil
Provide high-quality replacement coil, custom-fabricated to match AHU model and required specifications (rows, fins, capacity). -
Installation of New Coil
Position and secure the new cooling coil in the AHU housing, ensuring correct alignment and support. -
Reconnection of Piping & Insulation
Reconnect chilled water/refrigerant pipes with proper brazing or mechanical fittings, and apply new thermal insulation. -
Leak & Pressure Testing
Perform leak tests and pressure checks on piping and coil connections to ensure system integrity. -
Flushing & Chemical Cleaning (if needed)
Clean chilled water lines and coil internally to remove debris, scale, or contaminants. -
System Recommissioning
Start up the AHU system, check flow rates, temperature differential, and airflow. Calibrate controls and thermostats as needed. -
Final Testing & Handover
Verify performance under actual load conditions, document readings, and hand over job with test report and warranty (if applicable).