🔧 How Do I Qualify a Welding Procedure? (WPS Process Step by Step)
As a mechanical engineer working in pipe manufacturing, qualifying a welding procedure is not just a technical task ¡ª it¡¯s a guarantee of quality and safety.
Here¡¯s how to from a concept to a qualified WPS 👇
.;
1. Start with a pWPS (Preliminary Welding Procedure Specification):
I prepare a draft based on project specs and the applicable standard (e.g., API 5L or ASME IX).
It includes:
" Welding process: SAW / GMAW / SMAW
" Joint type & groove design
" Base metal grade
" Filler wire & flux
" Preheat & interpass temperatures
" Welding positions and passes
" Voltage, amperage, travel speed
.;
2. Perform the Welding Trial:
Using the pWPS, we weld a test coupon under controlled conditions.
All parameters are monitored and recorded carefully.
.;
3. Non-Destructive Testing (NDT):
Before we cut the coupon, we apply:
" Visual Inspection (VT)
" Ultrasonic Testing (UT) or Radiography (RT)
This ensures surface and internal weld soundness.
.;
4. Destructive Testing (DT):
We cut and test the coupon to verify:
" Tensile strength
" Bend test
" Impact test (for PSL 2 or low-temperature service)
" Macro/micro examination
" Hardness test (if required)
.;
5. Issue PQR (Procedure Qualification Record):
If all results meet the code and project requirements, we record them in the PQR, which validates the process.
.;
6. Final WPS Approval:
Based on the PQR, the Welding Procedure Specification (WPS) is issued and approved for production use.
.;
This cycle ensures that every weld meets performance expectations before it even reaches the field.









 
            
             
             
		

 
                 
 BR                                11593
BR                                11593                             VN                                6404
VN                                6404                             US                                4608
US                                4608                             AR                                1822
AR                                1822                             CN                                1296
CN                                1296                             SG                                702
SG                                702                             EC                                685
EC                                685                             GB                                525
GB                                525                             
         
        
 
        